Kole, 19 November 2026 - Construction of the Kole Town Council Piped Water Supply and Sanitation System in Kole District has reached 75.2% physical progress against 66.8% time elapsed, putting the contractor ahead of sc
This was revealed during the second site meeting and inspection conducted today 19th November 2026, by officials from the Water and Sanitation Development Facility-North (WSDF-N), CES, Kole Town Council, Corner Molem and Bala Town Council leadership.
The project is being undertaken by Reddy's Technical Services Limited under the direct supervision of WSDF-N.
Once completed, the system will serve a population of 27,486 people by the ultimate year 2044, it is a twenty years (20) project. It will cover Western A, Western B and Eastern B wards of Kole Town Council, Ogwangacuma and Apuru in Corner Molem, and Western A, Western B, Eastern A and Eastern B in Bala Town. The project is a 20 year expected to close in 202
The system components include:
1. Five pump stations, each with a guard house, pump house and a lined VIP latrine.
2. Energy source: A hybrid of solar and hydroelectric power.
3. Water source: Five production boreholes, each fitted with a pump.
4. Transmission mains: About 13.6 km of uPVC and HDPE pressure pipes.
5. Storage and treatment:
- A 150,000-litre cold-pressed steel tank elevated 18m above ground to serve Kole Town Council, with a chemical house equipped with an electric online dosing system for disinfection.
- A 100,000-litre tank for Corner Molem supply area.
- A 100,000-litre tank for Bala Town Council supply area.
6. Distribution network: About 47.8km of main distribution networks across the three supply areas, with pipes ranging from OD 160mm to OD 50mm.
7. Consumer connections: 600 domestic yard taps, 10 institutional yard taps and 6 public stand posts.
8. Water offices: Two fully furnished water offices for operations management in Kole Town Council and Bala Town Council.
9. Sanitation facilities at Okole Primary School: A 6-stance VIP latrine for boys with handwashing facilities, a 6-stance VIP latrine for girls with handwashing facilities, washroom and incinerator, and a 2-stance VIP latrine for staff.
The Ministry of Water and Environment, through the Government of Uganda, received funds through KfW to implement the Climate Resilience and Water Infrastructure for Refugees and Host Communities in Northern Uganda. One of the projects under the program is DKTI: Transformation to CO2 Neutral Water Supply, which aims to contribute to an energy-efficient and increasingly CO2-neutral water supply in Northern Uganda through optimization of water supply systems.
The meeting commended the contractor for the good progress and quality of work delivered, noting that the project was ahead of schedule, while highlighting key areas requiring continued attention, including extending water coverage to additional sub-counties, addressing structural cracks, resolving land issues at Atokimedi Pump Station, facilitating power connections at Wigweng and undertaking tree planting upon completion of critical civil works.