Sipi Irrigation Scheme Progress Review Meeting
On September 23, 2025, a meeting was held in Nabbongo Sub County, Bulambuli District, to review the progress of the Sipi irrigation scheme under the FIEFOC 3 project. The meeting, led by Engineer Ronald Kasozi, brought together officials from the Ministry of Water and Environment and Bulambuli District Local Government.
Key Takeaways:
- Community Notification: The social teams from the consultant and Ministry will coordinate to keep the community informed about project activities and changes.
- Grievance Handling: Grievances will be handled through the Grievance Redress Committees (GRCs).
- Project Implementation: The contractor sought support from stakeholders to complete the project within 24 months. Discussions focused on mechanisms to facilitate implementation, including stakeholder engagement, agronomy, natural resource management, and agri-business development.
- Progress Update: The consultant reported on survey and geotechnical investigation progress.
- Compensation: Compensation will be done in phases, and the community was advised to continue using their land until it’s designated for construction.
The meeting aimed to ensure the project’s smooth execution and effective community engagement.